| 1 |
Site Assessment |
The building site is reviewed for access, ground conditions, drainage, utilities, local regulations, and transport constraints. |
1–3 days |
Vehicle access, soil stability, required setbacks, utility connection points, and local permits. |
Approved site plan and installation strategy. |
Planning |
| 2 |
Design and Engineering |
The home layout, structural system, folding joints, openings, electrical routes, plumbing routes, and weatherproofing details are finalized. |
1–4 weeks |
Structural calculations, wind and snow loads, energy requirements, transport dimensions, and building-code compliance. |
Construction drawings and approved specifications. |
Design |
| 3 |
Foundation Preparation |
A level foundation is prepared before the folded structure arrives. Depending on the site, this may include a slab, piers, piles, or another engineered support system. |
1–3 weeks |
Accurate elevation, load-bearing capacity, drainage, anchoring locations, and curing time for concrete. |
Level and stable support platform. |
Site Ready |
| 4 |
Factory Fabrication |
Structural panels, frames, floors, roofs, doors, windows, insulation, and service components are manufactured and preassembled in a controlled facility. |
2–8 weeks |
Dimensional accuracy, material quality, connection points, protective packaging, and factory inspection. |
Folded or compact transport-ready home module. |
Fabrication |
| 5 |
Pre-Delivery Inspection |
The structure is checked before shipment to confirm that folding mechanisms, fasteners, protective layers, and pre-installed systems are secure. |
Half a day–2 days |
Transport locks, lifting points, panel protection, electrical and plumbing connections, and packing list. |
Inspection record and release for transport. |
Inspected |
| 6 |
Transport to Site |
The compact structure is loaded onto suitable transport equipment and delivered to the prepared foundation. |
Several hours–several days |
Route clearance, road restrictions, permitted transport dimensions, lifting access, weather, and delivery coordination. |
Folded home positioned near the foundation. |
In Transit |
| 7 |
Positioning and Unfolding |
A crane or other approved lifting equipment places the structure on the foundation. Hinged or engineered sections are then opened into their designed configuration. |
1–3 days |
Certified lifting plan, stable ground, qualified operators, correct alignment, and safe exclusion zones. |
Expanded structural shell in its final footprint. |
Assembly |
| 8 |
Structural Locking |
Bolts, welds, brackets, ties, and other specified connections are tightened or completed to secure the unfolded sections. |
1–3 days |
Connection torque, structural alignment, anchoring, floor level, roof geometry, and frame inspection. |
Stable and permanently connected structure. |
Secured |
| 9 |
Weatherproofing and Envelope Work |
Joints, roof edges, wall interfaces, windows, doors, and service penetrations are sealed to protect the home from water and air leakage. |
2–7 days |
Flashing, membranes, sealants, insulation continuity, drainage paths, and moisture control. |
Weather-resistant building envelope. |
Enclosed |
| 10 |
Utility Connections |
Electrical, water, wastewater, heating, cooling, ventilation, and communication systems are connected to the prepared site services. |
2–7 days |
Licensed installation, service capacity, grounding, pressure testing, circuit testing, and ventilation performance. |
Operational building services. |
Connected |
| 11 |
Interior Completion |
Remaining flooring, trim, cabinets, fixtures, appliances, lighting, plumbing fittings, and final finishes are installed. |
1–4 weeks |
Finish quality, moisture levels, safe clearances, fixture operation, and damage inspection. |
Move-in-ready interior. |
Finishing |
| 12 |
Final Inspection and Handover |
The completed home is inspected for structural safety, code compliance, utility operation, fire safety, water tightness, and general workmanship. |
1–5 days |
Required permits, inspection certificates, operating manuals, warranties, and homeowner orientation. |
Approved and handed-over folding home. |
Complete |